Three floors were included: metal railings, doors and windows and stained glass. At the same time, internal partitions are being removed in specific apartments.
2021December
30
9th floor
The 9th floor columns are being installed in Digomi and the whole floor will be filled in early January.
2021November
03
7th floor columns
The 6th floor is finished, the 7th floor columns are being installed.
2021August
31
Columns
Arrangements of the 4th residential floor are underway
2021August
24
2-3 floors wall
The walls of the 2nd and 3rd floors are being constructed
2021July
19
1st floor walls
A block is brought to the construction and we start removing the walls of the first floor
2021June
24
3rd floor
The third floor slab is being laid
2021May
31
2nd floor
Columns of the 1st floor of the residential building and the 2nd floor of the building are being prepared
2021May
18
Roofing
Roofing works of the first floor are underway
2021April
15
1st floor
1st (commercial) floor tile is laid. Preparations are underway for the insertion of the columns
2021March
15
Parking walls
Construction of minus floor columns and walls is completed, preparations for roofing are underway
2021February
09
Groundwork
The foundation has already been poured, a parking zone is being prepared